PROJECT HIGHLIGHTS
- Under construction, 2014
- Commercial WW, Greenfield
- Permit(s); Not required
- 10/NA/0.2 (TN/TP/Turbidity)
- Casino Toilet Flushing
- MMF Capacity: 0.075 MGD
- $39/gal
- 0.25 FTE (Full-Time Employee)

MBR technology is very versatile and can handle variations in flow and loadings in a Casino on weekends
DESCRIPTION
Angel of the Winds Casino has an OVIVO MBR since 2004. With addition of a hotel, gas station, convenience store, RV park, laundry facility restaurant, and an administrative building and community centre they were maxed out on weekends requiring an expansion. A greenfield MBR was built to handle the increased flow and loadings. The old MBR facility will be reused for WAS storage and also some offline EQ for the peak instantaneous flows.
LOCATION
,
IMAGES
PROJECT OVERVIEW
System Type(s) | OVIVO MBR |
---|---|
Previous Facility Type | OVIVO MBR |
Owner | Stilliguamish Tribe of Indians |
Engineer | RH2 Engineers |
Contractor | McClure & Sons |
Operations | Water & Wastewater Services |
Delivery Method | Negotiation; DB |
Time To Retrofit | 5 months |
Total Installed Project Cost | $2,956,000 |
PLANT DESIGN INFORMATION
Fine Screen Type | Bar Screen (FS) |
---|---|
Aperture or Slot Size | 2 mm |
Supplemental Aeration Technology | Fine Bubble, Strips |
MBR Blower Type | Positive displacement |
Solids Management Data | Hauling |
SCADA System | WonderWare |
Disinfection Method | Chlorine |
# Process Stages | 3 |
MBR (MEMBRANE ZONE) DESIGN
Filtration Mode | Pump assited gravity |
---|---|
# of Reactors : | 2 |
Submerged Membrane Unit (SMU) | OV400 |
# SMU | 8 |
Design Flux (MMF) | 8.59 gfd |
Minimum Temperature | 12°C |
Peak Factor | 2.8 |
# of Maintenance Cleans | 4 |