MBRCentral.com is your source of information for OVIVO® MBR products & services. Constantly evolving, MBRCentral.com will provide you with all the tools you need regarding OVIVO® MBR.
Search
  • HOME
  • CASE STUDIES
    • Featured Case Studies
  • SOLUTIONS
    • Ovivo®MBR
    • microBLOX®
    • EQuiptech™
    • stormBLOX™
  • DOWNLOADS
    • QUICK CARDS
    • VIDEOS
    • RESOURCE CENTER
  • ABOUT US
  • SUPPORT
  • CONTACT
  • LOGIN
  • CLIENT’S ZONE
    • LOGOUT
  • Sign In
  • CLIENT’S ZONE
    • LOGIN
    • LOGOUT
MBRCentral.com is your source of information for OVIVO® MBR products & services. Constantly evolving, MBRCentral.com will provide you with all the tools you need regarding OVIVO® MBR.
  • HOME
  • CASE STUDIES
  • SOLUTIONS
    • Ovivo® MBR
    • microBLOX®
    • equipTECH®
    • stormBLOX™
  • DOWNLOADS
    • Quick Cards
    • Videos
    • Resource Center
  • ABOUT US
  • SUPPORT
  • CONTACT
Menu

Return to previous page
Home Case Study

North Fork

North Fork

PROJECT HIGHLIGHTS

Commissioned September, 2008 Domestic WW, Greenfield Permit(s); Discharge 3/1/0.2    (TN/TP/Turbidity) Resort ⇒ Subsurface Drain Fields MMF Capacity: 0.12 MGD $31.25/gal 1 FTE (Full‐Time Employee)
Lead Operator, Dave Boshard, won the 2011 Utah WEA Outstanding Wastewater Operator of the Year Award (

DESCRIPTION

The Enviroquip® MBR was selected for the North Fork SSD due to ease of operation and a small footprint which is designed to provide consistent, high‐quality effluent.    The system removes BOD, suspended solids and nutrients such as nitrogen to extremely low levels for discharge. The plant currently discharges to a subsurface leach field. However, in the near future, UV disinfection will be added to the plant in order to produce Utah Class 1 effluent. Reuse effluent will be used for irrigation, fire protection, and grey water applications. This “hidden in plain sight” concept allows the plant to blend into the surroundings without having the obvious appearance of a wastewater treatment plant. This is a key benefit for such a high‐profile facility such as the Sundance Resort

LOCATION

Sundance, UT

IMAGES

GENERATE PDF VERSION

PROJECT OVERVIEW

System Type(s) Enviroquip ® MBR
Previous Facility Type Septic
Owner North Fork Sanitary Sewer District
Engineer Forsgren & Associates
Contractor Nelson Brothers Construction
Operations North Fork Sanitary Sewer District
Delivery Method Pre-Selection
Time To Retrofit 18 months
Total Installed Project Cost $3,750,000

PLANT DESIGN INFORMATION

Fine Screen Type Band Screen
Aperture or Slot Size 3 mm
Supplemental Aeration Technology Fine Bubble, Tubes
MBR Blower Type Positive Displacement
Solids Management Data Screw Press
SCADA System Wonderware
Disinfection Method Not Required
# Process Stages 2

MBR (MEMBRANE ZONE) DESIGN

Filtration Mode Pumped
# of Reactors : 2
Submerged Membrane Unit (SMU) RM200, KUBOTA®
# SMU 4
Design Flux (MMF) 11.2 gfd
Minimum Temperature 10°C
Peak Factor 2.0
# of Maintenance Cleans 2
Norfolk
North Lake