MBRCentral.com is your source of information for OVIVO® MBR products & services. Constantly evolving, MBRCentral.com will provide you with all the tools you need regarding OVIVO® MBR.
Search
  • HOME
  • CASE STUDIES
    • Featured Case Studies
  • SOLUTIONS
    • Ovivo®MBR
    • microBLOX®
    • EQuiptech™
    • stormBLOX™
  • DOWNLOADS
    • QUICK CARDS
    • VIDEOS
    • RESOURCE CENTER
  • ABOUT US
  • SUPPORT
  • CONTACT
  • LOGIN
  • CLIENT’S ZONE
    • LOGOUT
  • Sign In
  • CLIENT’S ZONE
    • LOGIN
    • LOGOUT
MBRCentral.com is your source of information for OVIVO® MBR products & services. Constantly evolving, MBRCentral.com will provide you with all the tools you need regarding OVIVO® MBR.
  • HOME
  • CASE STUDIES
  • SOLUTIONS
    • Ovivo® MBR
    • microBLOX®
    • equipTECH®
    • stormBLOX™
  • DOWNLOADS
    • Quick Cards
    • Videos
    • Resource Center
  • ABOUT US
  • SUPPORT
  • CONTACT
Menu

Return to previous page
Home Case Study

Skyline Ranch

Skyline Ranch

PROJECT HIGHLIGHTS

Commissioned February, 2005 Domestic WW, Greenfield Permit(s); Discharge 10/NA/NA    (TN/TP/Turbidity) Housing Development, Mobile Home Park ⇒ Irrigation MMF Capacity: 0.03 MGD $33.33/gal 0.25 FTE (Full‐Time Employees)
Tertiary effluent meets Title 22 requirements, and is applied for Golf Course Irrigation.

DESCRIPTION

Skyline Ranch Country Club, a private golf community near San Diego, CA, upgraded its water reclamation facility with ENVIROQUIP MBR Technology. The original treatment plant was constructed in 1973 to serve the Skyline Ranch Country Club (SRCC), a mobile home park of approximately 220 homes and a 9‐hole golf course. The park is privately owned by SRCC, LLC, but the Valley Center Municipal Water District owns and operates the treatment plant under RWQCB permit. The original plant was a conventional activated sludge package plant, which after 30+ years was in poor condition and required replacement or major overhaul.

LOCATION

Valley Center, CA

IMAGES

GENERATE PDF VERSION

PROJECT OVERVIEW

System Type(s) Enviroquip ® MPAC®
Previous Facility Type CAS
Owner Valley Center Municipal Water District
Engineer INVIROTREAT INC.
Contractor Skyline Ranch Country Club
Operations Valley Center Municipal Water District
Delivery Method Pre-Selection
Time To Retrofit 1 months
Total Installed Project Cost $1,000,000

PLANT DESIGN INFORMATION

Fine Screen Type Bar Screen
Aperture or Slot Size 2 mm
Supplemental Aeration Technology Medium Bubble, TransMax
MBR Blower Type Positive Displacement
Solids Management Data Hauling
SCADA System Wonderware
Disinfection Method None
# Process Stages 3

MBR (MEMBRANE ZONE) DESIGN

Filtration Mode Pumped
# of Reactors : 2
Submerged Membrane Unit (SMU) ES50, KUBOTA®
# SMU 6
Design Flux (MMF) 9.7 gfd
Minimum Temperature 20°C
Peak Factor 2.0
# of Maintenance Cleans 2